ABB – Student Housing – Site Fencing Changes

Project Office Construction Bulletin

WHO: Clark Builders Construction, Tyler Gagan, Project Manager

WHEN: Starting April 5, 2024, to June 15, 2024 (Subject to Change)

WHERE: Parking Lot 10, Infront of Building E, Athletics

WHAT: Upcoming modifications to the fencing layout by building E. To accommodate ongoing construction the following modifications to the fencing perimeter will be required.


Phase 1 – Starts April 5th, 2024

  • This phase will allow the construction team to install the underground infrastructure for EV charging stations.
  • Relocation of the fence will remove a dozen stalls from circulation.
  • Accessibility stalls will be relocated to the south side of Building E closer to the access ramp and to SUS]

Phase 2 – Starting May 15, 2024

  • This phase will allow for the student housing team to relocate the fire hydrant which is a requirement from the fire department for the project.
    • The fence perimeter will extend to include the area in the blue square above. A temporary detour route will be required as the pathway will be closed to pedestrians.
      • The detour route from parking lot 10 towards the green would include:
        • Path towards the Student Union Building, between building E and SUS.
        • Access through building E to the north-east entrance/exit


Phase 3 – June 15, 2024 – Final Fencing

  • Parking stalls not required to be blocked will become available again.
  • Pathway leading from lot 10 towards the green will be reopened
  • Accessible route to the front entry of building E and path to the green will remain and restored at the end of the project.

PROJECT OWNER: Lily Chan, UFV Capital Projects Director, (778) 982-0217, projectoffice@ufv.ca