Project Office Construction Bulletin
WHEN: Beginning Thursday, February 8th, 2024, All Day
WHERE: Building B, Level 1 and 2, and Drop Off Zone between Building, B, C and D
WHAT: Construction site mobilization will begin with the delivery of construction site materials. These deliveries are scheduled for 9 AM and 1 PM and will impact the walkway between B and D building. Construction personnel will be on site to ensure there is no risk for injury to any student or staff utilizing this area. All material offloading will be supervised and escorted on site.
The drop off area between C and D will be closed for the duration of the project for Turner Construction as a site laydown area.
PROJECT OWNER: Shelley Young, Senior Campus Designer, projectoffice@ufv.ca