WHO: Graham Construction, Dustyn Banks, Site Supervisor, 604-940-4500, Dustyn.Banks@graham.ca and Natalie Gagalka, Project Coordinator, 604-787-2605, Natalie.Gagalka@graham.ca
WHEN: Friday, February 24th, from 7AM to 3:30PM
WHERE: Building D, 3rd floor, but will affect entire building
WHAT: Fire alarm verification and testing will be conducted on February 24th between 7:00AM-3:30PM . During this period there will be periodic ringing of fire alarm bells and flashing of emergency strobes on all floors of D3. The ringing of bells and flashing of emergency strobes will not last longer that 15-30 seconds at a time.